87% of the Anthropic power will come from gas and 11% from coal in 2028
Reported by Hacker News1 source ↓
An analysis estimates that gas and coal will supply 87% and 11%, respectively, of power for Anthropic’s contracted U.S. data centers in 2028. The estimate includes on-site generation and grid power expected to meet the company’s added demand.
Key points
- Anthropic had contracted 15 GW of compute as of October 2026, with 5.9–9.6 GW tied to specific U.S. data center sites
- The analysis estimates 17–38 million metric tons of power-related CO2e emissions in 2028
- The analysis says Anthropic had disclosed no direct renewable-energy commitments in the U.S
Details
The analysis estimates Anthropic’s contracted U.S. data centers will draw power from on-site gas generation and from grid generators expected to meet the added demand. It says no grid renewable power is attributed to the company’s near-term use because it has not committed to new renewable capacity in the U.S.
The estimate covers 5.9–9.6 gigawatts of compute contracted to specific sites, out of 15 GW of total compute commitments reported as of October 2026. The analysis estimates those sites could produce 17–38 million metric tons of CO2-equivalent emissions in 2028; the range reflects uncertainty in average power use.
Written from coverage as of
Images
- Hacker News
- Hacker News
Stocks in this story
Change since open: 20 Nov to 21 Nov 2026
Last refresh