AI Data Centre Power Demand Is Outrunning the Grid: What Can Close It
Reported by discoveryalert.com and Fortune2 sources ↓
PJM’s 2028/2029 capacity auction procured 138,318 MW at its $325/MW-day price cap, but still fell 6,831 MW short of its reliability requirement. The article assesses which supply options could address the gap and on what timelines.
Key points
- PJM’s auction fell 6,831 MW short of its reliability requirement
- The auction procured 138,318 MW at the $325/MW-day price cap
- The article compares supply options by speed, firmness and scale
- A turbine ordered now would not be delivered until 2031, GE Vernova says
- Duane Arnold’s 615 MW reactor restart is targeted for Q1 2029, subject to NRC approvals
Sources
Details
Discovery Alert reports that PJM’s 2028/2029 auction was the second consecutive auction to fall short. PJM has linked the pressure to large new loads, including data centers, which the operator says can be built two to three times faster than much of the generation needed to serve them.
The article considers demand flexibility, reactor uprates and restarts, gas turbines, renewables with storage, and on-site generation. It argues that options should be assessed for when they can deliver, whether they are available at peak demand, and how much capacity they can provide; each faces constraints such as equipment lead times, interconnection delays or limits on when power is available.
The Department of Energy is targeting 5 GW from reactor uprates by 2029. The article cites Duane Arnold’s planned 615 MW restart, backed by a DOE loan of up to $1.9 billion and a 25-year Google power offtake; NextEra targets Q1 2029, subject to Nuclear Regulatory Commission approvals. GE Vernova reported 122 GW under contract and said reservations were open for 2031, while heavy-duty turbine delivery times are commonly about five years and can reach seven for some U.S. projects.
The article also notes uncertainty in demand forecasts: Lawrence Berkeley National Laboratory found some projections may be overstated, and Grid Strategies estimated possible overstatement of roughly 25 GW. It says forecasts can still strain planning because utilities must reserve capacity before the uncertainty is resolved.