Grid connection delays are pushing AI data centers toward on-site power, including gas generation and battery storage. The Financial Times reports that Britain’s gas use is set to rise as data center developers invest in fossil fuel generation.
Key points
- Omdia projects data centers could deploy 35 GW of behind-the-meter power by 2030
- Omdia forecasts annual battery storage investment could top $50 billion by 2030
- Caterpillar received a 2-GW equipment order for a West Virginia compute campus, with potential to expand to 6 GW
Sources
Details
Power Engineering reports that grid power shortages and longer interconnection queues are prompting data center developers to build or arrange power on site. Omdia projects behind-the-meter capacity at data centers could reach 35 GW by 2030, although many developers would prefer to buy electricity from utilities or independent power producers.
Battery storage is being used to pair with renewable generation, replace backup generators and buffer rapid changes in AI-related electricity demand. Omdia forecasts annual investment in battery energy storage could exceed $50 billion by 2030, up from nearly $10 billion in 2026. Oracle is incorporating batteries into its AI infrastructure to manage demand swings, according to the company’s infrastructure vice president.
Gas turbines are in short supply, and developers are ordering smaller turbines and mobile generation packages. Power Engineering reports that Frontier Infrastructure is buying 16 Baker Hughes NovaLT turbines for U.S. data center projects; Caterpillar has received an order for equipment rated at 2 GW for American Intelligence & Power’s Monarch Compute Campus in West Virginia, with possible expansion to 6 GW.
The Financial Times reports that delays connecting data centers to Britain’s electricity grid are leading developers to invest in fossil fuel generation, and says the country’s gas use is set to rise. Its excerpt provides no estimate for the scale or timing of that increase.