Brookfield and Drax plan AI data center at North Yorkshire power station
Reported by Drax Global, Reuters, Insider Media Ltd and 25 more outlets28 sources ↓
Drax, Brookfield and its Radiant platform plan a phased AI data center at Drax Power Station, targeting up to 100 MW from early 2028 and more than 1 GW eventually. Brookfield estimates the full project could attract more than £20 billion in investment.
Key points
- The first phase targets up to 100 MW of capacity from the first quarter of 2028
- A second phase could add 500 MW between 2028 and 2031
- Brookfield estimates investment could exceed £20 billion if the project is built in full
- The project still needs planning, regulatory and network approvals, commercial agreements and a tenant
- Drax and its partners plan public consultation and a community benefits fund
Sources
- Drax GlobalRead ↗Drax, Brookfield and Radiant announce £20bn partnership to deliver GW-scale data centre capacity at Drax Power Station
- ReutersRead ↗UK's Drax signs data centre deal with Brookfield and Radiant
- Insider Media LtdRead ↗Partnership to bring forward AI data centre at Drax Power Station - total investment could exceed £20bn
- CNBCRead ↗Brookfield targets $27 billion AI data center at power station. Energy firm Drax surges 8%
- Crypto BriefingRead ↗Brookfield targets $27B AI data center at Drax Power Station in North Yorkshire
Details
Drax’s agreement with Brookfield and Radiant covers development at the power station estate in North Yorkshire. The partners are seeking more than 1 GW of capacity there over time; the target date for reaching that level has not been specified. Brookfield’s estimate of more than £20 billion includes semiconductors, while the proposed initial investment for phase one is £2.5 billion.
The first phase would use grid power, with Drax aiming to supply up to 500 MW directly from its generation under a long-term power purchase agreement. The Register reports that direct supply would require approval from ministers and the Low Carbon Contracts Company, as well as other project approvals and agreements. No tenant has been named, and planning permission and final investment decisions remain outstanding.
Written from coverage as of