Envision says its system is powering live workloads at its Galaxy campus in Ulanqab, using solid-state transformers and batteries to supply 800V DC power. The campus is planned to reach 3GW capacity.
Key points
- The system converts 10kV AC directly to an 800V DC bus
- Battery storage provides rapid power support and minute-scale backup, Envision says
- The Galaxy campus began operating in August 2026
- The company did not disclose current live load or independently verified efficiency figures
- Envision plans to use the approach in its Mission Gobi program, targeting 5GW by 2030
Sources
- TMCnetRead ↗Envision Achieves World's First Commercial Deployment of Integrated 800V DC SST-Based Power System in Large-Scale AI Data Center
- BEST MagazineRead ↗Envision demonstrates integrated 800V DC power system at AI data centre
- pv magazine InternationalRead ↗Envision claims world first with 800 V DC architecture for AI data center
- Interesting EngineeringRead ↗World’s first 800V DC power system for data centers kicks off operations in China
- ET DatacentersRead ↗Envision deploys 800V DC power system in China AI data center
Details
Envision’s system combines solid-state transformers, battery storage and voltage-control equipment. The company says its Dubhe Controller coordinates these components in real time, with millisecond-level control intended to respond to GPU demand fluctuations. Gadget Review and BEST Magazine report that the installation is running live computing workloads.
Envision says the Galaxy campus in Ulanqab, Inner Mongolia, is planned to reach 3GW and eventually support up to one million AI accelerators. More than 80% of its power is expected to come from direct renewable connections, according to the company; these are planned future capacities and supply levels, not reported current operating figures.
The reports do not provide independently verified efficiency results. Gadget Review says the current live load and number of connected accelerators were not disclosed, while BEST Magazine reports that battery capacity, chemistry and backup duration were also not disclosed. Envision plans to deploy the technology through Mission Gobi, which targets 5GW of green AI data-center capacity in desert regions worldwide by 2030.