Spain’s government is expected to approve stricter data center rules before the Nov. 29 election, potentially putting billions of dollars in investment at risk. The proposal includes renewable-energy requirements and applies to projects already in development.
Key points
- The draft would require data centers to match 80% of their electricity use with renewable power hour by hour
- Projects already in development or awaiting grid connections would have five years to comply
- Aragón expects more than €60 billion in data center and digital infrastructure investment over the next decade
- Amazon and Microsoft say their Aragón plans are unchanged; Google has put a project on hold, according to El Mundo
Details
CNBC reports that the Spanish cabinet could approve the decree on Nov. 17 without parliamentary approval, ahead of the Nov. 29 elections. The government first proposed the measure in August and revised it on Oct. 26 after opposition. The draft would require data centers to source 80% of their electricity from renewables matched hour by hour, with possible loss of grid access for noncompliance.
The rules would also cover projects already being developed or waiting for grid connections, with a five-year transition period. Aragón, a northeastern region governed by the opposition Popular Party, is a focal point of the dispute and expects more than €60 billion in data center and digital infrastructure investment over the next decade. The Popular Party has said it would repeal the decree if it forms a government.
Amazon Web Services and Microsoft say their Aragón investment plans have not changed, while calling for predictable regulation. Google has put a multibillion-euro data center project on hold pending greater regulatory certainty, according to El Mundo, which cited anonymous sources. Industry group SpainDC says the proposal could put 80% to 90% of investment at risk; that estimate is the group’s claim.