Latitude Finds Data Center Power Contracts Cover 22% of Reported Load as Utilities Seek Power Plants
Reported by Tech Times1 source ↓
Utilities have signed contracts for about 120 GW of data center power, 22% of the 537 GW they report in their pipelines, according to Latitude Media data published Nov. 13.
Key points
- Latitude counts load as signed only when a customer has an executed service agreement
- The signed 120 GW is about 5.5 times the 22 GW operating in the territories covered
- Utilities are soliciting or considering about 37 GW of new generation
Details
Latitude Media’s data covers utilities in 53 U.S. service territories. The 537 GW pipeline figure includes reported demand at different stages, while the 120 GW figure represents load backed by executed agreements to take service. Utilities do not use a consistent definition when reporting data center demand, the article says.
The gap varies by utility: Georgia Power reports 80.1 GW of data center load, of which 12.8 GW is signed, according to Latitude’s platform. Jefferies analysts used a different method to assess 187 GW of disclosed commitments at regulated utilities; under their strictest category, formal electric service agreements, the total was 69 GW.
Written from coverage as of
Images
- Tech Times