NextDC says it will avoid future data center projects near homes after community opposition delayed an expansion at its M3 site in Melbourne. The company will add formal channels for residents to raise concerns.
Key points
- Expansion at the M3 site in West Footscray was delayed after protests over planned power poles
- NextDC will create a community consultative committee and provide a project website and complaint channels
- Shareholders issued a second strike against executive pay, but defeated a motion to spill the board
Sources
Details
NextDC’s chair, Doug Flynn, said the company would change where it builds in response to community sensitivities. Chief executive Craig Scroggie said the company needed to involve residents earlier and take responsibility for community support, alongside power, planning and construction.
The controversy concerned the proposed expansion of the M3 data center in West Footscray, where power provider Jemena paused construction of 22-metre poles amid community protests. The Guardian reports that the backlash contributed to NextDC’s share price falling 40%; it later recovered to more than $9 a share.
NextDC plans to establish a community consultative committee, including a regular forum for residents and local stakeholders. It also plans a dedicated project website and contact channels with set response times for complaints and inquiries.