SoftBank’s $3.7 billion equipment write-down drives its first quarterly loss in nearly two years
Reported by Tom's Hardware, Crypto Briefing, Bisnow and 2 more outlets
SoftBank reported a roughly $7 billion quarterly net loss after taking a $3.7 billion write-down on power equipment it no longer plans to use for data center projects.
Key points
- SoftBank had reserved more than 13 gigawatts of gas turbines, exceeding the needs of its planned 9.2-gigawatt Ohio power plant
- The company canceled some equipment orders but forfeited deposits and other advance payments
- SoftBank said the cancellations reflect changing project requirements, not a default on contracts
- Executives said the canceled orders do not mean SoftBank is reducing its current projects or development goals
- SoftBank said it cannot rule out further losses as its equipment requirements change
Sources
- Tom's HardwareRead ↗Softbank loses $3.7 billion on canceled AI data center gas turbine orders days after denying Elon Musk’s claim it was defaulting
- Crypto BriefingRead ↗SoftBank takes $3.7 billion hit after over-ordering turbines for AI data centers
- BisnowRead ↗Data Center Equipment Write-Down Drives SoftBank To Rare Quarterly Loss
- TechCrunchRead ↗SoftBank’s billion-dollar loss may have put a cap on AI’s natural gas ambitions
- Financial TimesRead ↗SoftBank’s failed bet on gas turbines for AI drove $3.7bn charge
Details
SoftBank’s turbine reservations were intended to secure power equipment amid long supply lead times. The company and its subsidiaries had made nearly $10 billion in advance payments for equipment before project plans were finalized, according to Bisnow. By September 30, cumulative advance payments for U.S. power-generation equipment stood at $9.48 billion, Crypto Briefing reports.
SoftBank canceled some reservations with GE Vernova and unwound other contracts, leaving it responsible for $3.7 billion in deposits and advance payments. Crypto Briefing reports that SoftBank has rights to conditional rebates of up to $2.1 billion on future turbine purchases.
The equipment had been procured for U.S. data center and power projects, including a planned 9.2-gigawatt Ohio power plant linked to an OpenAI-leased campus. SoftBank CFO Yoshimitsu Goto said the canceled orders do not mean the company is downsizing its projects, but warned that changes in equipment needs could lead to further losses.