The battle for megawatts: why restricting data centers is a strategic mistake
Reported by Fortune1 source ↓
Power must reach new computing capacity in time.
Key points
- New York introduced a pause of up to one year on some environmental permits for large data centers
- Nearly 12 GW of potential data center demand was in New York’s grid interconnection queue as of May 2026
- The essay says transformer lead times in the U.S. now exceed two years
- It calls for grid expansion, faster connections, nearby generation and energy storage
Details
Fortune’s essay points to restrictions and delays in several locations: Dublin’s new grid connections were effectively frozen for three years, Amsterdam imposed a moratorium on new facilities, and Frankfurt uses zoning rules to regulate their location. New York introduced a pause of up to one year on certain environmental permits for large data centers in July 2026. State officials said they would use the pause to assess effects on the grid and environment; nearly 12 GW of potential data center demand was in the state’s interconnection queue as of May 2026.
The essay argues that power supply and grid capacity, rather than construction limits, should be the focus. It cites International Energy Agency figures showing data centers accounted for about 70 TWh of the 800 TWh increase in global electricity consumption in 2025. Morgan Stanley estimates U.S. data centers could face a power shortfall of around 49 GW by 2028, while large transformer delivery times now exceed two years, compared with roughly 50 weeks before the pandemic.
The article says companies are seeking dedicated power: Microsoft agreed to buy electricity from the 835 MW Three Mile Island reactor, and Google’s agreement with Kairos Power calls for small modular reactors, with the first expected online by 2030. The essay recommends planning energy and digital infrastructure together, including expanding grids, speeding transformer production and connections, and encouraging nearby generation and storage. It also cites Ukraine’s 1.8 GW of distributed gas-fired generation and more than 500 MW under construction as an example of investment in local power resilience, while noting that Ukraine’s experience cannot be directly applied to large AI data centers.