The Unknown Hero Who Helped Stall a $5 Billion Data Center Plan
Reported by Gadget Review1 source ↓
Prince George's County tenant Taylor Frazier McCollum fought a $5 billion data-center plan, sparking a moratorium and national attention.
Key points
- A two-year county moratorium blocks new data-center approvals while officials update zoning and siting rules
- The proposed Landover campus remains unresolved; the moratorium does not cancel it
- McCollum's petition collected nearly 24,000 signatures
- The County Council voted 10-0-1 to require additional review and public involvement for certain data centers
Details
Lerner Enterprises had county planning approval for an 80-acre campus at the former Landover Mall site, less than a mile from where McCollum was living. County rules had allowed some data centers to bypass a full site-plan review and a second County Council vote, leaving residents without a formal opportunity to weigh in before approval. The council later voted 10-0-1 to close that gap; Council Member Wanika Fisher abstained.
McCollum organized a petition, attended county meetings and testified before Maryland legislators. The county established a data-center task force in 2025 and imposed a two-year moratorium on new approvals while it develops updated rules. The Landover project is delayed, not dead, and construction had been projected to start between 2026 and 2027.
Supporters project about $13.7 million in annual county tax revenue from the campus, according to Gadget Review's account of Baltimore Banner reporting. McCollum has suggested affordable housing, a sports complex or heritage tourism as alternatives, while acknowledging they may bring in less immediate revenue. Residents have raised concerns about emissions, air and water quality, noise, light pollution, and energy and water use; these are potential risks, not impacts from a facility that has not been built.