Statnett has paused new data center grid-capacity reservations and parts of its facility approval process while it develops technical rules. The halt is expected to end no later than August 1, 2027.
Key points
- Statnett reports 18,000 MW in additional connection requests, beyond 9,100 MW already in its capacity queue
- Facilities with approved technical requirements and existing connections are unaffected
- The government plans a licensing system to prioritize data centers it considers socially beneficial
- Statnett expects the pause to end by August 1, 2027, subject to technical rules and regulatory approval
Sources
- DatacenterDynamicsRead ↗Norway halts grid connection applications for new data centers
- Cyprus InformRead ↗Norway moves to restrict expansion of energy-intensive data centres amid AI boom
- QuartzRead ↗Norway's grid operator is pausing new power connection reservations for data centers
- CNBCTV18Read ↗Norway halts power connections for new data centers
- briefsRead ↗Norway pauses new power connection reservations for data centers
Details
The pause covers new applications for approval of facilities’ technical requirements and some previously submitted applications for direct connections to Norway’s 420 kV network. Statnett says data centers can make large, rapid changes in electricity demand, and it is developing rules to manage their effects on grid operations. The technical proposals will require regulatory approval.
The measure is not a general ban on grid connections. Facilities with approved requirements can still connect, existing connections are unaffected, and Statnett says some smaller facilities and regional-grid applications already being processed may proceed.
Statnett reports 800 MW of data center demand already connected, 4,200 MW with reserved capacity and 9,100 MW in the capacity queue, alongside requests for another 18,000 MW. The Norwegian government also announced plans for a licensing system covering data centers, with priorities including digital security, critical services and necessary AI computing capacity.